PrioritizationSAFeSpreadsheet · Excel & Google Sheets
WSJF calculator
Score features by cost of delay and job size, and let the sheet rank your backlog. Built for PI Planning prep and ART backlog refinement.
Live preview · try it
| Feature | Business value | Time criticality | Risk / opportunity | Cost of delay | Job size | WSJF | Rank | |
|---|---|---|---|---|---|---|---|---|
| 26 | 3.3 | 2 | ||||||
| 16 | 5.3 | 1 | ||||||
| 34 | 2.6 | 5 | ||||||
| 15 | 3.0 | 3 | ||||||
| 6 | 3.0 | 4 |
Cost of delay = value + time criticality + risk/opportunity. WSJF = cost of delay ÷ job size.
What’s inside
- Calculator with automatic ranking
- Scoring guide with the Fibonacci scale
- A worked example with 12 features
- Room for up to 50 features
How to use it
- 1List the features you’re deciding between
- 2Score one column at a time, as a group
- 3Estimate job size relative to the smallest item
- 4Review the ranking and discuss surprises